Here are a couple pictures of the overall site. The first one is looking southwest toward the raw material tanks. The building on the right will house the maintenance shop, plant offices, and control room. The second picture is looking northwest toward the finished product tanks and the LPG tank.
All the major foundations in the west processing area are now complete. The east/west pipe rack is now 100% complete and ready for pipe to be installed.