Construction Update - May 8, 2009
The power up of the 480v system is now complete. We also now have lights in the plant offices.
Here is the foundation for the hot oil heater being formed up.
An inside view of a raw material tank.
Construction Update - LPG Tank
The weather has been cooperating and we have been able to take advantage of it. Here is the LPG tank being put on the foundations.
Construction Update - May 2, 2009
All the major foundations in the west processing area are now complete. The east/west pipe rack is now 100% complete and ready for pipe to be installed.
These are the raw material tanks.
One of the separators being put in place.
Friday, May 1, 2009
Construction update - May 1, 2009
Our first piece of processing equipment got put on its foundation today!!!!
Construction Update - April 30, 2009
Things have been progressing quite well since the last update.......
Incoming raw material tanks
Here are some foundations for equipment in the processing area:
And here is the first pipe going in the pipe racks:
Newer Posts
Older Posts
Home
Subscribe to:
Posts (Atom)
Our fuel
Followers
Blog Archive
▼
2009
(18)
►
July
(4)
►
June
(5)
▼
May
(5)
Construction Update - May 8, 2009
Construction Update - LPG Tank
Construction Update - May 2, 2009
Construction update - May 1, 2009
Construction Update - April 30, 2009
►
April
(4)