Thursday, April 23, 2009

Construction update - April 12, 2009


We have had over 18,000 safe work hours since the end of January!!
  • 90% complete on excavation of the West Process Area
  • Started steel erection for the east/west pipe rack.
  • All piles have been completed.

East / West Pipe Rack


Piles for the HDO reactors.

Tuesday, April 21, 2009


Here are some of the existing pipe racks that we are preparing for use.

And here is the area after being cleaned up with the new foundations for the raw material tanks in place.

It was a cool week this week and just right for construction work. Here we are preparing the area where the raw material tanks that hold the incoming raw materials will built.